Protea Hotel King George Renovation

We were appointed as quantity surveyors and project managers for the hotel’s bar and lounge upgrade. The project introduced a sleek redesign of the bar and lounge area, a new outdoor seating space, and a modern swimming pool. Enhanced with contemporary furnishings and improved lighting, the space now offers a sophisticated environment for guests. The outdoor area provides a stylish setting to enjoy the weather, while the swimming pool adds a touch of luxury. These updates have elevated the guest experience and bolstered the hotel’s appeal in George.

Project Value: R 3 Million
Completion Year: 2023

The Towers Shopping Centre

QS3 Group successfully completed a 9,000 square meter retail shopping centre in Bloemfontein, a R105 million project delivered on time in 2015. Our exceptional project management and quantity surveying skills ensured seamless coordination, strict adherence to timelines, and precise budget management. We tackled challenges proactively, delivering a high-quality project on schedule. Our quantity surveying team provided accurate cost estimates, detailed budgeting, and rigorous financial oversight, optimizing resource use. This project stands as a testament to QS3 Group’s commitment to blending design, functionality, and financial management, creating a vibrant and future-ready retail destination.

Project Value: R 105 Million
Completion Year: 2015

Nike Shapa Soweto

Completed in 2021 in Soweto, South Africa, the Nike Sporting Facility featured a basketball court, a FIFA-accredited football field, an athletics track, a skate park, and a dance studio. As quantity surveyors for this R 63 million project with Nike, we managed cost estimation, budget control, and financial reporting, ensuring the project was completed within budget. The facility not only enhanced community engagement but also promoted health and fitness, setting a new standard for community sports hubs.

Project Value: R 63 Million
Completion Year: 2021 

Africa Pride Irene

We managed a transformative project in Irene, Pretoria, with a final value of R94 million, completed in 2018. The project involved upgrading an existing restaurant, constructing new hotel rooms, developing an outdoor seating area, and introducing a modern conference facility. Our role encompassed overseeing all phases, ensuring timely completion, and maintaining high-quality standards. The result was a premier destination that enhances guest experiences with contemporary amenities and sophisticated design.

Project Value: R 94 Million
Completion Year: 2018 

Protea Hotel Fire & Ice Menlyn

We served as Quantity Surveyors and Project Managers for a R 220 million 4-star Protea Hotel development in Menlyn, Pretoria, completed in 2015. The project featured 178 rooms across a 6-story structure with a mega basement. Our quantity surveying role involved detailed cost estimating, budgeting, and financial management, ensuring value for money. As project managers, we coordinated all aspects of construction, managed schedules and resources, and ensured quality and timely completion. Our comprehensive oversight ensured the project’s successful delivery within budget and on schedule.

Project Value: R 220 Million
Completion Year: 2015 

CUT Engineering Facility

We acted as Quantity Surveyors for the Engineering Faculty upgrade, overseeing cost management and financial planning. The project included major enhancements to infrastructure, laboratories, and amenities, providing a modern learning environment. Our role ensured the project was completed efficiently within budget, showcasing our commitment to precision and excellence in managing complex upgrades.

Project Value: R 57 Million
Completion Year: 2012

Protea Hotel OR Tambo

We successfully developed a 214-bed 4-star hotel in Kempton Park, Johannesburg, featuring a diverse range of room types, a restaurant, bar, conference facilities, and a fitness center. As quantity surveyors, we managed cost estimation, budgeting, and financial oversight. In our role as project managers, we directed planning, scheduling, and coordination, effectively addressing challenges such as site constraints and design changes. The project, valued at R101 million, was completed on time and within budget, incorporating sustainable practices and innovative solutions to meet the highest standards.

Project Value: R 101 Million
Completion Year: 2009 

Protea Hotel Kimberley

As project managers and quantity surveyors, we oversaw the construction of Protea Hotel Kimberley, a 120-room hotel in Kimberley. Situated opposite the Big Hole in Kimberley, the hotel offers a prime location for visitors. Our role included project planning, cost management, quality control, and stakeholder coordination.

The project faced challenges, including adverse soil conditions that required special foundation solutions. Despite these and other issues like design changes, we successfully delivered the project on schedule and within budget. The hotel features a restaurant, recreational facilities, and conference facilities, meeting high hospitality standards.

Completion Year: 2007 

Protea Hotel Willow Lake

As project managers and quantity surveyors, we oversaw the construction of Protea Willow Lake, a 94-room hotel located in Bloemfontein. The hotel is strategically situated to serve both business and leisure travelers. Our role included project planning, cost management, quality control, and stakeholder coordination.

Despite challenges like design changes, we successfully delivered the project on schedule and within budget. The hotel features a restaurant, recreational facilities, and conference facilities, meeting high hospitality standards.

Completion Year: 2009 

Protea Hotel Nelspruit

As project managers and quantity surveyors, we oversaw the construction of a 94-room Protea Hotel in Nelspruit, ensuring adherence to budget and timeline. Our role included project planning, cost management, quality control, and stakeholder coordination. Despite challenges like supply chain disruptions and design changes, we successfully delivered the project on schedule and within budget. The hotel features a restaurant and recreational facilities, meeting high hospitality standards.

Completion Year: 2004 

Protea Hotel Mahikeng

As project managers and quantity surveyors, we oversaw the construction of Protea Hotel Mahikeng, a 99-room hotel in Mahikeng, ensuring adherence to budget and timeline. Our role included project planning, cost management, quality control, and stakeholder coordination. Despite challenges like supply chain disruptions and design changes, we successfully delivered the project on schedule and within budget. The hotel features a restaurant, recreational facilities, and conference facilities, meeting high hospitality standards.

Completion Year: 2007 

Protea Hotel Bloemfontein

As project managers and quantity surveyors, we oversaw the construction of Protea Hotel Bloemfontein, a 94-room hotel located in Bloemfontein. The hotel is strategically situated to serve both business and leisure travelers. Our role included project planning, cost management, quality control, and stakeholder coordination.

Despite challenges like design changes, we successfully delivered the project on schedule and within budget. The hotel features a restaurant, recreational facilities, and conference facilities, meeting high hospitality standards.

Completion Year: 2002 